EETS prepared procurement specifications for the long lead time equipment early in the design process, allowing the 200 MVA power transformer and 230 kV breaker to be purchased and placed in the manufacturing queue before construction documents were finalized. This removed the transformer and breaker from the critical path and preserved the downstream construction schedule.
The construction bid documents were structured as three sequential packages: civil and underground work first, followed by above-ground structure installation, with electrical equipment installation, connection, and startup as the final package. This sequencing allowed civil earthwork and underground conduit to proceed while structural fabrication continued in parallel, and deferred energized electrical work until the physical infrastructure was in place. The result was a compressed but executable construction schedule that kept all three phases of work advancing simultaneously where possible.
The full EPC design package produced by EETS covered the complete substation expansion: control and relaying one-lines, plans, elevations, arrangements, details and schedules, technical specifications for the 200 MVA 230:34.5 kV transformer, 2000A 230 kV power circuit breaker, disconnect switches, cabling and bussing, control building layout, and the protective relaying and revenue metering systems. Engineering calculations covered insulation coordination, CT saturation, battery sizing, protection system design, and ground grid design, all prepared and sealed by EETS as Engineer of Record.
The Phase III expansion of Russell Substation was completed on schedule in spring 2012, adding 128 MW of wind generation capacity to SMUD’s portfolio. The substation now operates with a 200 MVA transformer, full 230 kV and 34.5 kV protection and switching capability, and a new control building with modern protective relaying and metering. The four underground collection circuits serve all 80 Phase III turbines and are integrated into the overall wind farm electrical system alongside the Phase I and II installations.
EETS brought continuity, technical breadth, and schedule discipline to a project that required all three.
EETS’s engagement with the Solano Wind Farm began years before Phase III construction, with the Phase II analysis that resolved the voltage and power factor issues following that expansion. That prior work gave EETS a detailed understanding of the existing system at Russell Substation before Phase III design began: how the collection system performed under load, how the substation interfaced with the PG&E transmission system, and where the existing protection scheme would need to be extended. Engineers who already know a facility design more efficiently and with fewer hidden assumptions than those starting from scratch.
The Phase III scope required electrical engineering across a wide range: power system modeling and analysis, 230 kV substation design, 34.5 kV collection system design, protection and control, utility interconnection coordination, and the full EPC drawing and specification package. EETS provided all of it as lead electrical engineer, and sealed the design as Engineer of Record. Holding the EOR role means accepting professional responsibility for the technical correctness of the work. It also means a single point of accountability for the electrical design, which simplifies coordination with the owner, the civil team, and the contractor.
The decision to prepare early procurement specifications for the transformer and 230 kV breaker, and to structure the construction documents as three sequential bid packages, reflected a clear-eyed understanding of where schedule risk lived on this project. Heavy electrical equipment has long lead times that cannot be compressed. Civil and underground work does not require energized electrical equipment to be on site. Identifying those dependencies and structuring the delivery accordingly was the design decision that made a compressed construction schedule achievable.